Demolition and Sanitizing:
- Academic Wings
- Demolition in the academic wings is completed as of today
- Sanitizing is being completed in the K-2 and 3-5 Wings today
- The flood cut in the library will be sanitized tomorrow for drying to occur over the weekend
- Gym
- The gym floor demolition is scheduled to begin Monday.
- Movers have relocated materials from the gym to locations within the building and to off-site storage this week
- The entire gym floor will be replaced
Air Quality Testing
- Pre-occupancy air sample tests are slated for early next week
- Results will be back by early the week after next
- If the test results are positive and we receive clearance to reoccupy parts of the building, we will continue with our phased reopening plan with moving 7-8 back into the building as soon as is practicable.
- To minimize the loss of any further instructional time, materials will be moved over the weekend or during vacation.
- Construction areas are being / will be sealed off from the rest of the building.
Construction/Reconstruction
- Sheetrock has arrived on site and is in the process of being installed throughout the flood impacted areas
- Painters will be following along behind the sheetrock crews
- Flooring/Carpets will be installed after the painting is complete
Have a great weekend!